Airbus has started work on a 6,221-square-metre extension at its Belfast site. The building is to house a third autoclave, wing tooling and lifting equipment; the company also plans electrical, office and access upgrades. Completion is scheduled for the first half of 2028. The investment links a local facility to a higher A220 production rate.

Belfast does not perform final aircraft assembly: the site manufactures and integrates the A220 family’s composite wings, as well as control surfaces. A wing is a major structural assembly whose manufacture and finishing must feed the aircraft assembly flow. The additional autoclave—a heated, pressurised vessel used to process composites—is intended to expand that upstream industrial capacity.

The production schedule presented with Airbus’s annual results called for 12 A220s a month in 2027, then 13 in 2028. That ramp-up takes place amid continuing pressure on parts of Airbus’s supply chain. The Belfast extension prepares upstream capacity for the final-assembly lines; by itself, it cannot ensure that every link will reach the same pace.

The project also sits within Airbus’s effort to bring Airbus-related work packages made by Spirit AeroSystems under its ownership. In 2025, Airbus signed a definitive agreement to acquire the relevant A220 activities, including Belfast wing production. In that agreement, Airbus said it wanted to stabilise supply operationally and financially. Direct control of critical production and an expanded site are complementary industrial tools.

Belfast’s wings feed, among other facilities, the A220 final-assembly line in Mirabel, Québec. The programme has grown beyond its origins as Bombardier’s C Series: Airbus became its majority partner in 2018 and, with the Québec government, its sole owner in 2020. The 2020 agreement retained assembly in Mirabel and provided for other production work to move there. The Belfast expansion thus connects two major parts of the programme.

Commercial results give a sense of the volume the system must handle, without guaranteeing a future rate. Airbus delivered 93 A220s in 2025, up from 75 in 2024, and booked 49 gross orders for the model that year. Across the company, the backlog exceeded 8,700 aircraft. The new facility is one part of the ramp-up; orders, engines, suppliers and deliveries will determine the pace that can actually be sustained.