Inaugurated on 15 September at the Jean-Luc Lagardère site, the centre brings together finishing, airline reception and customs procedures. Sixteen aircraft positions are near the final assembly line. Airbus presents the 35,000-plus-square-metre complex as a way to smooth customer handover; it is not an additional assembly line.

In 2018, Airbus opened a fourth A320 line in Hamburg, linking automation, digital tools and a flexible layout to a target rate of 60 aircraft a month by mid-2019. The company also inaugurated an enlarged delivery centre there, with more customer areas and processes it said would be more efficient. Investing in assembly and customer handover together is therefore not new; Toulouse is now adapting that approach to its own site.

In Toulouse, in 2021, after a pause linked to the Covid crisis and production cuts, Airbus restarted work to modernise an A320/A321 line in Toulouse. Planned for the former A380 building, it was to replace an original line and add flexibility for A321 assembly.

The building’s first line delivered its first A321neo to Pegasus Airlines in December 2023. Airbus described that handover as the start of the line’s ramp-up, with a stated goal of helping produce 75 A320 Family aircraft a month in 2026. The rate schedule has since shifted, but that customer delivery shows the site’s operational role was already under way.

In Q1 2026, Airbus delivered 81 A320 Family aircraft and identified Pratt & Whitney as the main constraint on the ramp-up.

The new centre supports the planned ramp-up, whose timetable also depends on suppliers. Back in February, Airbus had set its A320 Family target at 70–75 aircraft a month by the end of 2027, then 75 thereafter, citing a shortage of Pratt & Whitney engines. Reuters reported at the time that the two companies had yet to agree engine supply volumes for either 2026 or 2027. The centre can smooth handover of completed aircraft; engine supply, meanwhile, governs the assembly lines’ ramp-up.