Airbus inaugurated a second A320 Family final assembly line in Toulouse’s former A380 Jean-Luc Lagardère building on 15 June. It now counts ten lines across Toulouse, Hamburg, Mobile and Tianjin. The opening adds industrial flexibility to a network facing a record order book.

The conversion began before this ceremony. The first Toulouse line, inaugurated in July 2023, already occupied the former A380 hall and was due to ramp up gradually. Airbus said it could assemble A321s and employ around 700 people. Digital controls and automated logistics were already part of its setup. The second line therefore extends a site conversion planned over several years rather than an improvised response to the spring 2026 order book.

Demand is concentrated on the A321neo. At the end of May, Airbus reported an A320 Family backlog of 7,499 aircraft, including 5,615 A321neos, figures also carried by Air Journal. That proportion helps explain the priority given to lines able to assemble the family’s largest single-aisle model. Flexibility between variants lets Airbus adjust output to the delivery dates promised to customers.

The immediate bottleneck also lies beyond assembly halls. Airbus said in April that Pratt & Whitney engine delivery commitments were weighing on its 2026 ramp-up. It now targets 70 to 75 A320 Family aircraft a month by the end of 2027, followed by a stable rate of 75. The ramp-up will therefore depend as much on engine deliveries as on available assembly stations.

As early as October 2025, Airbus described new A320 Family lines in the United States and China and planned completion of the second Toulouse line by mid-2026. The four-country network is meant to serve global demand over several years. The industrial challenge is to synchronise engine and other supplier deliveries with assembled airframes so more stations translate into handovers to airlines.