On July 18, CFM International announced FAA and EASA certification of the LEAP-1B high-pressure turbine durability kit. The change targets engines exposed to heat and dust in regions such as the Middle East and India. CFM says the kit will double time on wing in those conditions.

The kit addresses the high-pressure turbine, where ingested particles can erode blades operating at high temperatures. GE Aerospace, CFM’s co-owner with Safran, describes dust testing and analysis of data from other engine families as inputs to the work.

The programme draws on experience with the LEAP-1A that powers Airbus A320neo aircraft. CFM said in July that 40% of that fleet had the HPT kit and 70% the reverse bleed system. The engine maker is preparing to extend them to the 1B variant used on Boeing 737 MAX aircraft.

The other modification, the reverse bleed system (RBS), moves air through the engine after shutdown to limit carbon deposits in fuel nozzles. CFM announced initial engine-level certification for the 1B, while aircraft-level approval remained in process. The RBS entered service on the 1A in 2024; CFM reports more than two million activations.

CFM’s current programme page sets a full production cutover for early 2027. In November 2025, CFM said it was working with Boeing to introduce the upgrades to 737 MAX operators. Rollout involves both production lines and maintenance shops, as well as a supply of parts.

The 1B powers the 737 MAX family, whose operators do not have the engine choice available on the A320neo between LEAP-1A and Pratt & Whitney’s GTF. Airlines will judge the change through shop visits, parts availability and intervals achieved on their own routes. Test figures and 1A experience provide a starting point; the 1B’s own record will emerge as the retrofit spreads.

Documents and references