On 2 July GAO published a review of 104 US weapon programmes. It examines technical risks accepted at the start. Average time to field a capability in the largest programmes now exceeds twelve years. The auditor recommends that accelerated projects use mature technology or develop uncertain elements separately. The Pentagon agreed to that recommendation, which remains open for follow-up.

The middle tier of acquisition was designed to prototype or field capabilities within two to five years. GAO found in 2023 that the pathway needed programmes willing to defer an immature feature and take user feedback on an initial version. It also reported inaccurate or incomplete programme data that weakened central oversight. Speed therefore depends on disciplined choices and measurement, not simply on the name of an acquisition route.

Another GAO investigation, published in December 2024, compares US service acquisition policies. It finds an iterative structure in the software pathway but a less complete one in urgent, middle-tier and major-capability routes. For systems combining hardware and software, testing and military-user feedback should shape successive versions. That institutional difference helps explain July’s findings: permission to use a rapid route does not itself give a programme a workable sequence of deliveries.

Another GAO report, published in December 2025, places testing at the centre of the problem. For major and middle-tier programmes, Pentagon rules still fall short on early tester involvement, iterative trials and continuing user feedback. Problems discovered late in evaluation have already contributed to delays. GAO therefore recommends bringing testers into acquisition strategy from the outset and structuring validation around an initial usable capability. The department has yet to complete those policy changes.

The delays did not begin with July’s report. In 2025 GAO already found that a first weapon-system version took almost twelve years on average and that earlier reforms often worked around slow processes without changing them. Its testimony cited the T-7A as a severely delayed case. The new assessment gives acquisition leaders a measurable test: shorten delivery while retaining honest data on maturity, cost and the capability actually fielded.