On 24 August, Australia laid the keel of its first Hunter frigate at Osborne. The government said work had begun on 20 of the ship’s 22 major blocks. BAE Systems Maritime Australia leads the programme, which supports more than 2,500 direct jobs and 5,000 supply-chain jobs. The navy is expected to receive the first ship in the early 2030s.
Hunter derives from Britain’s Type 26, but the Australian configuration combines the locally developed CEAFAR2 radar, the US Aegis combat system and an interface developed by Saab Australia. The navy gives it a primary anti-submarine role, alongside air-defence and surface-warfare missions. Integrating technologies from several countries helps explain the engineering task facing the yard and its suppliers. The ships are intended to form a six-vessel class.
The planned series has changed scale. The design selected in 2018 was intended for nine frigates; the 2024 surface-fleet review retained six and added eleven general-purpose frigates to the future force. Those ships address a separate need for presence, escort and strike. Hunter must therefore provide specialized anti-submarine capability within a more varied fleet. The decision also concentrates the Osborne programme on a shorter run than originally envisaged.
Australia’s national audit office identified an eighteen-month delay to the start of construction in 2023, largely linked to immature design, along with cost pressure. Its review also questioned how value for money had been demonstrated in procurement. Laying the keel shows physical progress since that finding. Control of weight, system interfaces and schedule will become clearer through assembly and trials. The earlier audit is historical context, rather than an assessment of the ship as built.
The first steel intended for the ship was cut in June 2024, when the construction contract for the first three frigates was signed. At that point the government expected initial operational capability in 2034 and a twenty-year build programme for the class. Osborne is also scheduled for other major naval work, including AUKUS submarines. Hunter’s pace therefore bears on skills and industrial capacity beyond the first hull. The keel ceremony marks one step in that longer production sequence.
Documents and references
- Australian Defence MinistersKeel laying for first Hunter frigate
- Royal Australian NavyHunter Class frigate
- Australian Defence MinistersEnhanced lethality surface combatant fleet
- Australian National Audit OfficeProcurement of Hunter Class Frigates
- Australian Defence MinistersFirst step in boosting undersea warfare and strike capability