On 16 July Safran began PHILEAS tests at Istres. Supported by France’s DGAC, this full-scale hybrid-electric demonstrator is scheduled for nearly 300 ground-test hours over six months.

Two electrical machines equip the high- and low-pressure shafts. As motors or generators, they inject or extract power. Safran tests transfers between shafts and aircraft systems.

The programme builds on earlier Safran Electrical & Power work. In December 2023 the company reported that a GENeUS 300 machine had completed 500 hours of ground testing and generated 300 kW at about 96% efficiency, with a power density of 10 kW/kg. It had also demonstrated switching between motor and generator functions, a central capability for controlling the energy exchanges sought through hybridisation.

Hybrid-electric capability is among the technologies in CFM RISE, launched by Safran and GE in 2021. The programme also explores an Open Fan architecture for a future generation of single-aisle engines. CFM targets more than 20% lower fuel use and carbon dioxide emissions than today’s most efficient engines. Its roadmap includes component, module and full-engine builds followed by flight testing.

In June 2025 CFM said Safran was preparing a hybridisation campaign on a full engine alongside more than 350 RISE component and module tests already completed. Those included tests on the low-pressure turbine and compressor, bearings and Open Fan blade-pitch controls. Full-engine electrical integration was intended to extend this work beyond individual assemblies.